Schemes with gross command area up to 2000 Hectares fall under this category. The detailed physical and financial status of ongoing and completed minor irrigation schemes comprising flow schemes, lift schemes, deep tube wells and shallow tube wells are given in the table below. (as on March, 2021)
Status of Schemes | Flow Irrigation Schemes | Lift Irrigation Schemes | Deep Tube Wells | Shallow Tube Wells | Total | PMKSY Points |
---|---|---|---|---|---|---|
Completed | 1614 | 483 | 593 | 192 | 2882 | 2348 |
Ongoing | 378 | 139 | 444 | 21 | 982 |
2431 (Ph I) 4920(Ph II) |
Total | 1992 | 622 | 1037 | 213 | 3864 |
4779 (Ph I) 4920(Ph II) |